The Key Livelihood Projects of Dalian Municipal Government Have Landed in Orderly Manner
2022-08-05 18:27

In July, the Municipal Government Supervision and Examination Office included the key livelihood projects of the Municipal Government into the key projects in the second half of 2022 for listing supervision, and 35 projects of 15 key livelihood projects continued to land. Among them, 7 projects have achieved the annual target, 12 projects have achieved the July target ahead of schedule or exceeded the July target, 13 projects have achieved the July target on schedule, and 3 projects have adjusted the July node target after being reported to the municipal government for approval.

 

Seven projects have achieved the annual target

 

In July, two new projects were added to achieve the annual target, namely:

 

Since July, the project of "Improving the Basic Living Standards of Urban and Rural Minimum Living Allowances and Extremely Poor People" has paid security funds according to the new standards, achieving the annual target. The urban minimum living standard has been raised from 780 yuan to 850 yuan per person per month, with an increase of 8.97%. The rural minimum living standard in Pulandian District, Wafangdian City and Zhuanghe City increased from 580 yuan per person per month to 660 yuan, an increase of 13.79%; In other areas, rural and urban minimum living standards are consistent. The basic living standard of centralized and decentralized support for destitute people in the city has increased from 1,560 yuan per person per month to 1,700 yuan, an increase of 8.97%; The basic living standard of centralized and decentralized support for destitute people in rural areas of the city has increased from 1,014 yuan per person per month to 1,105 yuan, an increase of 8.97%.

 

Since July, the project "Improving the Basic Raising Standards for Orphans and de facto Unaccompanied Children" has paid basic living allowances according to the new standards, achieving the annual target. The basic living standard of centralized and decentralized orphans in the whole city has increased from 2,340 yuan and 1,605 yuan per person per month to 2,550 yuan and 1,710 yuan per person per month, with an increase of 8.97% and 6.54% respectively.

 

In the first half of the year, five projects have completed the annual target ahead of schedule:

 

The project "Improving the Subsidy Standard for Care Services for the Disabled", The bid raising notice was issued on April 15th, Since January 1, 2022, the city's subsidy for care services for the disabled has implemented a unified standard in the whole city. The subsidy standard for centralized care institutions has been raised from 68 yuan to 75 yuan per person per day, the subsidy standard for home care services has been raised from 200 yuan to 220 yuan per person per month, and the subsidy standard for day care institutions has been raised from 25 yuan to 35 yuan per person per day, achieving the annual target two months ahead of schedule.

 

In February, 18 A-level scenic spots, such as Laohutan Ocean Park and Forest Zoo, were organized to participate in the project of "Implementing Free Tour Project for Citizens' Scenic Spots". The registered population in Dalian traveled free of charge on their birthdays, and a fellow registered population in Dalian received a half-price discount, completing the annual target one month ahead of schedule.

 

In the project of "adding 100 new taxis", 100 Geely British TX5 new taxis were put into operation in February, and the annual target was achieved one month ahead of schedule.

 

The project of "Implementing the Publicity and Promotion Project of 'One Mobile Phone Traveling to Dalian'" has completed all the development and construction of the intelligent cultural travel platform of "Traveling to Dalian", including five functional areas and eight modules, and started trial operation on May 25, completing the annual target four months ahead of schedule.

 

In July, 156 community trainings were organized in the project of "Building Safety Training and Education System for Group Prevention and Control", and 225 news articles were published in China Emergency Management News, Liaoning Daily, Dalian Daily, Dalian Evening News, Peninsula Morning News, Today Headline, Netease, Tencent and other media, which achieved the annual target five months ahead of schedule in June.

 

12 projects ahead of schedule or exceeded the node target in July

 

Two projects completed the node target in July ahead of schedule:

 

Pulandian District, Wafangdian City and Zhuanghe City involved in the project of "repairing and rebuilding 200 km rural roads in large and medium-sized areas" all completed the project bidding work before June 1, and completed the node target in July nearly two months ahead of schedule. At present, the construction is being organized in an orderly manner.

 

The project of "Implementing 25 Rural Drinking Water Safety Maintenance Projects", involving Pulandian District, Wafangdian City and Zhuanghe City, has completed the project bidding work before June 23, and completed the node target in July one month ahead of schedule. At present, the construction is being organized in an orderly manner.

 

Ten projects exceeded the node target in July:

 

By the end of July, all regions had completed more than 20% of the building renovation tasks, and the whole city had completed 36.7% of the building renovation on average, exceeding the target task of 20%.

 

As of the end of July, the project of "Implementing Gas Safety Improvement Project" has completed the replacement of 88,000 natural gas users in 125 communities, and completed 110% of the target of replacing 80,000 households; Completed the transformation of municipal gas pipeline network and courtyard gas pipeline network for 145.5 kilometers, and completed 162% of the goal of 90 kilometers; Completed 578.17 km of gas riser renovation, and completed 231% of the target of 250 km renovation.

 

By the end of July, the total progress of the project in the whole city was 43%, exceeding the target of 20%. Among them, the preliminary work is "four discussions, first trials and two openness", the preliminary design has been completed, 80% of bidding or government procurement has been completed, the operating rate is 70%, and the project construction progress is 7%.

 

The project of "Completing the Renovation of Dangerous Houses of 191 Rural Low-income Groups and Other Key Objects" has started 188 dilapidated houses and completed 107 dilapidated houses in the city, exceeding the target of starting the renovation of dilapidated houses.

 

As of the end of July, the total progress of household toilet projects in the whole city was 58%, exceeding the target of 30%. Among them, the preliminary work stage ("four discussions, first instance and two openness", preliminary design, bidding or government procurement, etc.) has been completed, with an operating rate of 80% and a project construction progress of 20%. The total progress of public toilet projects in the whole city is 48%, and the preliminary work stage has been completed, with an operating rate of 80% and a project construction progress of 11%.

 

In the project of "Newly Opening and Adjusting 6 Bus Lines", on July 20th, the site investigation around the 24th City Community of China Resources created necessary conditions for the extension and adjustment of No.35 bus lines. In the first half of the year, newly opened No.2002 and No.2007 bus lines, optimized and adjusted No.2001 bus lines, and exceeded the node target of newly opening and adjusting 2 bus lines.

 

The project of "Implementing Employment Promotion Services" has organized a business training meeting at the end of April to launch innovative and entrepreneurial projects to attract well-known university students; From May to June, 494 people passed the preliminary examination after organizing declaration, preliminary examination and credit verification; At present, it is the review stage, and 300 people have been reviewed. By the end of July, a total of 81,000 new jobs had been created in cities and towns, and 135% of the target of 60,000 new jobs in July had been achieved; The registered urban unemployment rate is 3.13%, which is 0.87 percentage points lower than the control target of 4%; Help 71 zero-employment family members achieve employment, and keep zero-employment families dynamically cleared.

 

In the project of "Adding 15 Public Kindergartens", in July, two public parks were newly opened, namely Gold Park Kindergarten in Jinpu New District and Xiangzhou Capital Kindergarten in Xigang District. By the end of July, 4 new public parks had been opened, and 870 public degrees had been added, exceeding the target of increasing 720 public degrees.

 

In the project of "Holding 100 Mass Cultural Activities", 9 mass cultural activities were completed in July, 2 more than originally planned. Among them, there are 4 exhibitions, 2 non-legacy activities, 1 Korean mass cultural activity and 2 mass reading promotion activities.

 

In the project of "Configuring, Renewing and Repairing 3000 Sets of Outdoor Fitness Equipment", 120 sets of outdoor fitness equipment were updated and repaired in July, 20 more than originally planned.

 

Three projects adjust the node targets in July

 

Due to the adjustment of the winning supervision company and the approval of the municipal government, the project of "Implementing the Reconstruction and Expansion Project of Eight Roads" led by the municipal center postponed the July target of "signing the construction and supervision contract and organizing the construction in an orderly manner" to August.

 

The project of "Implementing 40 Urban Road Lighting Construction Projects" led by the Municipal Center, due to the adjustment of the bidding control price of the project, was submitted to the municipal government for approval, and the July target of "completing supervision and construction bidding" was postponed to August.

 

The "Xinhua Road Primary School" project under the responsibility of Zhuanghe City Municipal Government, due to the adjustment of construction scheme, was submitted to the municipal government for approval, and the target of "completing the main frame construction" in July was postponed to August.

 

13 projects completed the July node target on schedule

 

The project of "Implementing the Broadcast Signal Coverage Project of Highway Traffic Tunnel in the Main City" has issued a project bidding announcement. "Complete the comprehensive transportation hub project of Dalian North Railway Station" and complete the project progress as planned. In the project "Improving the Living Allowance Standard for the Disabled with Difficulties and the Nursing Allowance Standard for the Severely Disabled", a request for raising the two subsidy standards for the disabled has been drafted. The project of "Implementing the Pilot Project of Improving Home Care Services" has started to assess the ability of the elderly. In the project of "Promoting the Expansion of Old Age Allowance", a training meeting on aged care services in the whole city has been held. "Implementing the Demonstration Fever Clinic Construction Project of Municipal Medical Institutions", the design scheme of fever clinic has been completed; "Implement free prenatal screening and diagnosis services and neonatal disease screening projects", and the screening rates are up to standard. "Implementing the Project of Encouraging and Supporting the Supply of Pratt & Whitney Nursery Services", the Interim Measures for the Identification and Management of Pratt & Whitney Demonstration Nursery Institutions have been issued. "Implementing the Family Planning Special Family Contact Assistance Project", a meeting to promote the fertility care project has been held. In the project of "Introducing High-end Performances and Selling 10,000 Professional Theater Cultural Huimin Cards", a total of 4,628 cultural Huimin Cards have been sold. The project of "Organizing 200 Performances for Benefiting the People" has completed 149 performances for benefiting the people. The project of "Implementing the Anti-fraud Project of the Whole Society" has avoided the loss of more than 80 million yuan through the early warning system. The project of "Implementing the Project of Police Situation" focuses on dispatching three-level fire control management and potential safety hazard investigation.

 

In the next step, the Municipal Government Supervision and Examination Office will do a good job in tracking the work progress and controlling the time nodes, and urge all responsible units to strengthen overall planning, strengthen the sense of responsibility and payment, and complete the objectives and tasks to the letter as planned. At the same time, the municipal center and the Zhuanghe City Municipal Government are required to reverse the construction period and pay close attention to the construction of the projects that adjust the objectives and tasks in July, and report the progress every week until they catch up with the original planned progress.